Written by: Gerrit Koldewee
2025
Onderwerp: Installatie laadstations.
Historie:
Beleid en doelstellingen:
Ontwerp:
Realisatie:
2025
Subject: Charging Station Installation
History:
Initiatives to install charging stations began in 2023, but the maximum supply of 60 kW made this unfeasible.
A higher connection capacity will not be implemented before 2029.
In 2024, legislation mandated charging stations at publicly accessible parking spaces by January 1, 2025.
Policy and Objectives:
Objective: Sustainable Investments
Design:
The grid operator can supply a maximum of 60 kW, while current consumption is a maximum of 50 kW, leaving insufficient capacity at the outset.
The legal requirement conflicts with limited supply capacity.
In 2024, it was decided that solar panels would help meet a large portion of electricity demand, creating capacity on sunny days.
Full electricity supply to charging stations is not guaranteed on cloudy or low-sun days.
The entire electricity system is connected to an EMS (Energy Management System) to regulate power supply for self-consumption and charging stations.
Implementation:
Charging stations were installed by Chargepoint Zevenaar, a local specialist installation company.
Chargepoint is also a Business Member.